Solar Free Reviews
About
Solar Free is a distributor of Conergy solar panels across Australia, with particular emphasis on the Australian Capital Territory and Victoria.
Panel brands previously installed
Inverter brands previously installed
The views expressed by reviewers are theirs alone, and do not necessarily reflect those of Peacock Media Group, which makes no representations as to the accuracy of the reviews. For our full disclaimer and further information, see our Terms of Use and our Review Guidelines.
Solar Free Reviews (11)
Show Most Recent reviews from All time across Australia
Average Scores
Value for money
Quality of System
Installation
Customer Service
- 5 star 0
- 4 star 3
- 3 star 3
- 2 star 3
- 1 star 2
View Timeline
06 March 2013
06 November 2012
Original Review on 30-05-2011:
I searched the internet for stories from others while I was researching solar panels and installation companies. I drew a blank. So I am detailing my story here in the hope that it might shed some light for others.ACTEWAGL Energy Shop over the phone (early April 2011) quoted about $5000 for a 1.5kW system: 8 panels, inverter in garage, 33% deposit, refund if not do-able by 30/6/2011.
Solar Free (early April 2011) quoted over the phone using Google Maps or similar to look at the house roof. Quoted $2995 for a 1.5kW system, subject to a site visit. A weatherproof inverter would be installed on the exterior of the house near the meter box.
They weren't interested in doing a site visit until after the quote was accepted. At the time this seemed like a reasonable cost-saving measure. Quote accepted and 10% paid up front as requested. (note: a friend mentioned in May that Solar Free's up front payment had increased to 50%) Two working days later an email arrived with a large number of attachments. These included (1) the ACTEWAGL connection form, which was to be signed and returned by snail mail or by hand before any further action was possible, and (2) the contract for installation that I had agreed to by paying the 10%. The contract included a clause that said that verbal advice from the company was not to be relied upon! After a few weeks I was contacted by Field Force (subcontracted by Solar Free, along with 2 other companies, to carry out installations) to organise a date for the site inspection. I accepted the earliest time and date offered. The site inspection was carried out approx 6 weeks after the quote was initially accepted. The guy was about 2 hours later than agreed, although I was his first visit for the day. He wasn't interested in getting onto the roof, although I had a ladder ready due to the earlier experience with Green Tiger. About 1 week later I received the quote for additional works: about $1300 for a meter box upgrade. I phoned the ACTEWAGL Energy Shop (AES) for a sanity check since this was different to what Green Tiger said. AES said a 60cm x 60cm meter box was required and estimated a cost of $800-$1200 to have a box upgraded. So I agreed and paid the ~$1300. A request from Solar Free for the remaining 90% quickly followed. I paid. A couple of days later I was advised by phone that due to the weather my installation would be sometime after 6th June. So no date for installation yet, approx $4300 paid for a 1.5kV system so far, and I'm still wondering if this is a good idea.
18 months later we asked Wendy: "Are you happy with the performance of your system so far?"
To my knowledge, the 1.5 kW system has never reached this peak. This could be due to the angle of inclination and facing-direction of the panels.17 September 2012
Original Review on 25-05-2011:
The telephone experiences with the installer I selected have been very good. Friendly and efficient. The pre-installation guys were polite although they were very quick with the inspection and did not advise me of an extra charge (an upgrade required to our power box to modernize for solar) until I received a letter from a contracted panel up-grader which wished payment within 5 days. Although price was fair, it would have nice to be told directly at pre-installation rather than later from a contractor.Note: Unfortunately, as installation has not yet been completed I cannot vouch for quality and value at this stage. All I can say is pricing is very competitive and with components being German built (I know Germans put Australia to shame as far as national solar output and have always been fantastic engineers and designers), these were the main factors for me.
16 months later we asked Tim: "Are you happy with the performance of your system so far?"
The Conergy system has performed completely to expectations and even exceeded them. We have been enjoying reduced energy costs and are very glad we committed to this Government led programme when we did (before the cancellation of new uptake).12 September 2012
Original Review on 30-05-2011:
Not yet installed. Please contact me again in 2 or 3 weeks.Comments so far:
Supplier and the installers are not local;
Communication not as good as I would like;
Money was requested before installation;
Little or no flexibility for choice of panels;
Decision was rushed because of political pressure; but
Price seemed right at the time.
16 months later we asked Rod: "Are you happy with the performance of your system so far?"
No. I expected 10 panels to generate more than I consume - even in winter. I have yet to see how they perform in summer.We need some sort of reference point to compare with.
12 September 2012
Original Review on 18-05-2011:
Not yet turned on - installed only a week ago. Not entirely happy about the requirement to pay full (net) amount as soon as approved by ACT without a completed installation, but it worked out.16 months later we asked Sue: "Are you happy with the performance of your system so far?"
The system is 1.52Kw and paid for our summer bills and about half of our winter ones. It seems fine if perhaps of less than sufficient size to supply our full energy requirements. but it was the size we could then afford.08 August 2012
16 June 2011
22 May 2011
02 May 2011
29 April 2011
by the electrician for extra switches etc. The worst part is that you have to pay the full amount
before they send you the contract to sign. My advise is to deal with a local supplier and contractor.
17 April 2011